The U.S. Army Corps of Engineers (USACE) began Fiscal Year 2025 (FY 25) channel maintenance dredging on the Mississippi River Ship Channel with the industry hopper dredge GLENN EDWARDS (Manson Construction) on March 2, 2025. The most recent crest on the Mississippi River at the Carrollton Gage was recorded at 16.67 feet on May 1, 2025, at 1800 hours. River stages continue to recede but are expected to remain above 10 feet into mid-June (2025).

DUSTPAN DREDGES(S) WORKING ON THE CROSSINGS ABOVE NEW ORLEANS:

HURLEY: The USACE dustpan dredge HURLEY is scheduled to commence dredging at Baton Rouge Front Crossing (Mile 231.0 Above Head of Passes [AHP]) today. The dustpan dredge is on scene at Baton Rouge Front and expected to commence dredging soon.

WALLACE McGEORGE: The industry dustpan dredge WALLACE McGEORGE (Pine Bluff Sand & Gravel) is expected to commence dredging at Alhambra Crossing (Mile 190.5 AHP) tomorrow.

INDUSTRY HOPPER DREDGE(S) WORKING in the area of SOUTHWEST PASS (SWP):

NEWPORT: The NEWPORT (Manson Construction) is undergoing minor maintenance but is expected to resume dredging this Thursday (May 22, 2025). The NEWPORT is working on the second FY 25 Early Award hopper contract (Gulf Coast Regional Hopper Contract Early Award #2-2024).

DODGE ISLAND: The DODGE ISLAND (Great Lakes Dredge & Dock) is working on assignment at Cubits Gap (Mile 3.3 AHP to Mile 1.8 AHP). The hopper dredge commenced dredging operations in SWP on April 7, 2025.

GLENN EDWARDS: The hopper dredge GLENN EDWARDS is undergoing minor repairs but is also expected to resume dredging on Thursday (May 22, 2025). The GLENN EDWARDS is working under Southwest Pass Hopper Early Award #1-2024, the first of the two Early Award hopper dredge contracts for Fiscal Year 2025 (FY 25). The Bar Pilots adjusted their flocculation based high tide transit restrictions for inbound vessels with drafts of 38 feet or greater on May 7, 2025. The official Notice is attached. The flocculation event is reported to be improving some as is typical as river stages decrease, but the transit restriction/recommendation remains in effect.

GOVERNMENT HOPPER DREDGE(S) WORKING IN SOUTHWEST PASS (SWP):

WHEELER: The USACE hopper dredge WHEELER is working in SWP from Mile 10.4 Below Head of Passes (BHP) to Mile 12.2 BHP under Readiness Exercise #4-2025. The WHEELER is tentatively scheduled to work Readiness Exercise #5-2025 from June 9 to June 20 (2025) in SWP.

CUTTERHEAD DREDGE(S) WORKING IN THE NEW ORLEANS HARBOR:

The USACE recently advertised a bid opening for a cutterhead dredge to work on channel maintenance in the New Orleans Harbor. The apparent low bidder was Weeks Marine, additional details will be provided when the contractual details are available.

CUTTERHEAD DREDGE(S) WORKING IN SOUTHWEST PASS (SWP):

R.S. WEEKS: The R.S. WEEKS (Weeks Marine) is currently dredging at Mile 13.18 BHP and is concentrating on the heaviest shoaling in the assignment from Mile 12 BHP to Mile 13.5 BHP. The cutterhead will complete this reach first and then focus on the full assignment starting at Mile 9.0 BHP and extending to Mile 15.0 BHP on the western side of the Channel. The cutterhead began dredging in SWP on May 3, 2025.

MISSISSIPPI RIVER STAGES AND FORECAST UPDATES:

The Carrollton Gage (New Orleans) reading at 1400 hours today was 13.20 feet, with a 24-hour change of - 0.14 feet. The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Predictions (28-Day Forecast) for the Carrollton Gage issued today forecasts that stages will continue an extended fall, although the forecast stages will remain at 11.7 feet from May 29 to June 5 before resuming a slow fall toto 10.3 feet on June 17 (2025).

The Baton Rouge Gage reading at 1400 hours today was 35.63 feet, with a 24-hour change of - 0.14 feet. The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Predictions (28-Day Forecast) for the Baton Rouge Gage issued today forecasts that stages will continue a slow extended fall to 27.0 feet on June 17 (2025).
The NWS 28-Day long-range forecasts only include precipitation expected to fall in the next 48-hours.

The 168-hour (7 Days) Quantitative Precipitation Forecast (QPF) precipitation map below is reproduced from the National Weather Service.

“Forecasters at the WPC and its predecessor organizations have been making Quantitative Precipitation Forecasts since 1960. Quantitative Precipitation Forecasts, or QPFs, depict the amount of liquid precipitation expected to fall in a defined period of time. In the case of snow or ice, QPF represents the amount of liquid that will be measured when the precipitation is melted. Precipitation amounts can vary significantly over short distances, especially when thunderstorms occur, and for this reason QPFs issued by the WPC are defined as the expected "areal average" (on a 20 x 20 km grid) in inches.”

168-HOUR QPF FORECAST:

[cid:image001.gif at 01DBC99E.13DD5650]

*The 168-hour QPF predicts heavy precipitation across a large portion of the central United States along the Mississippi and Ohio River Basins.

“The graph below is reproduced from NOAA’s National Weather Service website and represents an experimental product to account for the complexity of accurately predicting long-range precipitation.  These forecast projects stage levels based on expected precipitation for 2 days (top) and 16 days (bottom) and was developed within the North American Ensemble Forecast System (NAEFS) computer model and highlights Quantitative Precipitation Forecasts (QPF).  Along with the forecasts, a shaded area is also provided to indicate uncertainty for the forecast each day in the future. These plots are experimental and not an official forecast product.”

NEW ORLEANS QPF:

[NORL1_67_28d_forecast_error_plot.png]

The graph below represents the Year-to-Date (2025) plotted river stages for the Carrollton Gage from January 1 to May 20 (2025):

[Chart titled, Mississippi River at New Orleans (Carrollton) (01300) From 01/01/2025 To 05/20/2025]

Please see the attachments to support the Dredge Update.

With You,
Sean
Sean M. Duffy, Sr.
Executive Director

Standing By Channel: (504) 338-3165

Big River Coalition
http://bigrivercoalition.org<http://bigrivercoalition.org/>

This E-Mail transmission (and/or the documents accompanying it) may contain information belonging to the sender that is confidential, privileged and/or exempt from disclosure under applicable law.  The information is intended only for the use of the individual(s) or entity named above.  If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution or action taken in reliance on the contents of this information is strictly prohibited.  If you have received this E-Mail transmission in error, please immediately notify us by return E-Mail or telephone to arrange for the return of its contents (including any documents).

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.gif
Type: image/gif
Size: 62644 bytes
Desc: image001.gif
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0001.gif>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 204500 bytes
Desc: image002.png
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0002.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.png
Type: image/png
Size: 14286 bytes
Desc: image003.png
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0003.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Lower Mississippi River (LMR) Dredging Update 52025.pdf
Type: application/pdf
Size: 2274158 bytes
Desc: Lower Mississippi River (LMR) Dredging Update 52025.pdf
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0002.pdf>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 20250507_093650_Raven_Scan[2][2].pdf
Type: application/pdf
Size: 404030 bytes
Desc: 20250507_093650_Raven_Scan[2][2].pdf
URL: <http://lists.listserve.louisianamaritime.org/pipermail/louisianadelegation/attachments/20250520/f92dbf13/attachment-0003.pdf>


More information about the Louisianadelegation mailing list